Conveyor debugging steps
- Feb 09, 2017 -

(1) all equipment carefully after installation and commissioning conveyors, meet design requirements.

(2) the reduction gear, moving parts raise the appropriate lubricant.

(3) after you install conveyors meet the requirements of each single device for manual work of the test and combined commissioning conveyors in order to meet the requirements of action.

(4) the commissioning electrical parts of the conveyor. Includes general electrical wiring and commissioning to make good performance, design features and status.